[1]朱建国,徐伟,沈杰,等.多事件干扰下工期拖延责任分摊计算[J].东南大学学报(自然科学版),2012,42(1):188-193.[doi:10.3969/j.issn.1001-0505.2012.01.035]
 Zhu Jianguo,Xu Wei,Shen Jie,et al.Calculation on construction delay responsibility sharing with multi-event interference[J].Journal of Southeast University (Natural Science Edition),2012,42(1):188-193.[doi:10.3969/j.issn.1001-0505.2012.01.035]
点击复制

多事件干扰下工期拖延责任分摊计算()
分享到:

《东南大学学报(自然科学版)》[ISSN:1001-0505/CN:32-1178/N]

卷:
42
期数:
2012年第1期
页码:
188-193
栏目:
经济与管理
出版日期:
2012-01-18

文章信息/Info

Title:
Calculation on construction delay responsibility sharing with multi-event interference
作者:
朱建国徐伟沈杰成虎
(东南大学土木工程学院,南京 210096)
Author(s):
Zhu JianguoXu WeiShen JieCheng Hu
(School of Civil Engineering, Southeast University, Nanjing 210096, China)
关键词:
工期拖延争议时差叠加和发散效应
Keywords:
construction delay claims float superposition and divergent effect
分类号:
F284;TU72
DOI:
10.3969/j.issn.1001-0505.2012.01.035
摘要:
针对利用网络分析技术计算工期索赔时常发生的叠加和发散效应,分析了网络计算叠加效应和发散效应的成因,得出了网络计算叠加效应和发散效应分别产生于初始时差和过程时差重复利用的结论.提出了多事件干扰下工期拖延责任分摊原则和计算方法.该方法认为时差应为承包商和业主双方共同所有,直接针对双方因时差优先使用权产生的争议,即网络计算叠加效应和发散效应产生的附加值.当在时差的使用上不发生争议时,任何一方都可以随意使用时差.如果发生争议,则争议时差应在业主和承包商之间平均分摊.该方法坚持了公平原则,很大程度上化解了承包商和业主之间的争议,同时对共同延误也具有适用性.
Abstract:
Compared to the independent analysis of contractor-risk and owner-risk delay events, integrated analysis for all delay events using CPM(critical path method) scheduling techniques will have different results which are called the phenomenon of superposition effect and divergent effect. Root causes of this phenomenon are discussed in detail in this paper. Superposition and divergent effect are closely related to the reuse of total float and newly created total float time for both the contractor and the owner. Under current scheduling practices, total float is considered to be an asset for both the contractor and the owner to use for free. Newly created total float is produced by project delays caused by the contractor or the owner. Based on the consideration of the ownership and utilization of total float and newly created total float, the principle for the allocation of the outcome of superposition and divergent effect has been proposed. The new concept makes a direct response to the focus of disputes for superposition and divergent effect. Calculation methods for the allocation of delay responsibility are proposed.

参考文献/References:

[1] Society of Construction Law.Delay and disruption protocol [EB/OL].(2004)[2011-03-04].http://www.eotprotocol.com.
[2] Gothand K D.Schedule delay analysis:modified windows approach [J].Cost Engineering,2003,45(9):18-23.
[3] Householder J L,Rutland H E.Who owns float? [J].Journal of Construction Engineering and Management,1990,116(1):130-133.
[4] de La Garza J M,Vorster M C,Parvin C M.Total float traded as commodity [J].Journal of Construction Engineering and Management,1991,117(4):716-727.
[5] Wickwire J M,Warner T,Berry M R.Construction scheduling:preparation,liability,and claims [M].New York:Wiley Law Publication,1991.
[6] de Leon Gui Ponce.Float ownership-some recommendations [J].Stratagem,1982,1(1):55-72.
[7] de La Garza J M,Prateapusanond A,Ambani N.Preallocation of total float in the application of a critical path method based construction contract [J].Journal of Construction Engineering and Management,2007,133(11):836-845.
[8] Ambani N.Bookkeeping procedures for the application of the concept of preallocation of total float [D].Blacksburg,VA,USA:University of Virginia Polytechnic and State,2004.
[9] 彭慧杰.基于TIA的工期延误分析[J].青岛建筑工程学院学报,2005,26(1):91-96.
  Peng Huijie.TIA for the analysis methods of the claims for extension of time [J].Journal of Qingdao Institute of Architecture and Engineering,2005,26(1):91-96.(in Chinese)
[10] 郭汉丁,郑丕谔,郝海.工期索赔分析中网络计算的叠加和发散效应[J].西安建筑科技大学学报:自然科学版,2003,35(1):59-62.
  Guo Handing,Zheng Pi’e,Hao Hai.Effect piling up and effect weakening of the network calculation in damage claims on time limit analysis [J].Journal of Xi’an Univ of Arch &Tech:Natural Science Edition,2003,35(1):59-62.(in Chinese)
[11] 姚小刚,凌传荣.多因素影响下工期索赔的复杂性[J].同济大学学报:自然科学版,2001,29(3):362-365.
  Yao Xiaogang,Ling Chuanrong.Complication study on compensate time limit for project under double factors affection [J].Journal of Tongji University:Natural Science Edition,2001,29(3):362-365.(in Chinese)

备注/Memo

备注/Memo:
作者简介:朱建国(1984—),男,博士生;成虎(联系人),男,博士,教授,博士生导师,pmri@seu.edu.cn.
基金项目:江苏省普通高校研究生科研创新计划资助项目(CXZZ11_0182).
引文格式: 朱建国,徐伟,沈杰,等.多事件干扰下工期拖延责任分摊计算[J].东南大学学报:自然科学版,2012,42(1):188-193.[doi:10.3969/j.issn.1001-0505.2012.01.035]