[1]吕伟华,缪林昌.刚性桩复合地基桩土应力比计算方法[J].东南大学学报(自然科学版),2013,43(3):624-628.[doi:10.3969/j.issn.1001-0505.2013.03.032]
 Lü Weihua,Miao Linchang.Calculation method of pile-soil stress ratio of rigid pile composite foundation[J].Journal of Southeast University (Natural Science Edition),2013,43(3):624-628.[doi:10.3969/j.issn.1001-0505.2013.03.032]
点击复制

刚性桩复合地基桩土应力比计算方法()
分享到:

《东南大学学报(自然科学版)》[ISSN:1001-0505/CN:32-1178/N]

卷:
43
期数:
2013年第3期
页码:
624-628
栏目:
土木工程
出版日期:
2013-05-20

文章信息/Info

Title:
Calculation method of pile-soil stress ratio of rigid pile composite foundation
作者:
吕伟华缪林昌
东南大学岩土工程研究所, 南京 210096
Author(s):
Lü Weihua Miao Linchang
Institute of Geotechnical Engineering, Southeast University, Nanjing 210096, China
关键词:
路堤 刚性桩 复合地基 桩土应力比 中性点
Keywords:
embankment rigid pile composite foundation pile-soil stress ratio neutral point
分类号:
TU470
DOI:
10.3969/j.issn.1001-0505.2013.03.032
摘要:
为了准确简便地预测路堤在荷载下发生的沉降变形,必须对桩基复合地基的桩土应力比进行合理正确的评价计算. 针对高速公路地基处理中采用刚性桩复合地基的情况,假设路堤土中基底相对位移下土柱间滑移面剪应力垂直分布,考虑桩顶上刺入路堤、桩端下刺入下卧层以及桩侧负、正摩阻力非线性分布,分析了路堤-桩-地基土整体在应力与位移协调下的相互作用. 通过迭代计算求得路堤内等沉面高度与加固区中性点位置,得到戴帽刚性桩复合地基在路堤荷载下的简单桩土应力比计算公式. 通过2个工程实例实测数据对提出的计算方法进行了合理性验证,分析结果表明该方法对于填土路堤高度大于2倍桩净间距的工况计算结果具有较高的精度.
Abstract:
In order to predict embankment settlement more accurately and simply, the pile-soil stress ratio of rigid pile composite foundation should be adequately evaluated. In the load effect analysis, a vertical shearing plane due to relative displacement at embankment fill base is adopted. Then a simplified theoretical calculation model is deduced, in which the behaviour of pile upward and downward puncture deformation is considered, and the distribution of pile lateral friction above and under the neutral point is assumed to be linearly dependent on stress state. Afterwards a calculation formula of the pile-soil stress ratio of rigid pile composite foundation is proposed with pre-determination of equal settlement plane height in fill and neural point position within pile length by iterative computation. The presented method is validated by comparing analytical solutions with the observed results from a newly constructed highway project and a widening highway project. Results show that the proposed method obtains more accurate results of pile-soil stress ratio when the fill height is more than twice the pile net spacing.

参考文献/References:

[1] 折学森. 软土地基沉降计算 [M]. 北京: 人民交通出版社, 1998: 182-188.
[2] 傅景辉, 宋二祥. 刚性桩复合地基工作特性分析 [J]. 岩土力学, 2000, 21(4): 325-329.
  Fu Jinghui, Song Erxiang. Analysis of rigid pile composite foundations working performance [J]. Rock and Soil Mechanics, 2000, 21(4): 325-329.(in Chinese)
[3] 朱世哲, 徐日庆, 杨晓军,等. 带垫层刚性桩复合地基桩土应力比的计算与分析[J]. 岩土力学, 2004, 25(5): 814-823.
  Zhu Shizhe, Xu Riqing, Yang Xiaojun, et al. Computation and analysis of ratio of pile stress to soil stress of rigid pile composite foundation with cushion [J]. Rock and Soil Mechanics, 2004, 25(5): 814-823.(in Chinese)
[4] 赵明华, 陈庆, 张玲. 考虑桩顶刺入变形的刚性桩复合地基桩土应力比计算 [J]. 公路交通科技, 2009, 26(10): 39-43.
  Zhao Minghua, Chen Qing, Zhang Ling. Calculation of pile-soil stress ratio of rigid pile composite foundation with consideration of piles upward puncture deformation [J]. Journal of Highway and Transportation Research and Development, 2009, 26(10): 38-43.(in Chinese)
[5] Naughton P J. The significance of critical height in the design of piled embankments [C]//New Peaks in Geotechnics, Soil Improvement. Denver, USA, 2002: 1-10.
[6] 陈云敏, 贾宁, 陈仁朋. 桩承式路堤土拱效应分析 [J]. 中国公路学报, 2004, 17(4): 1-6.
  Chen Yunmin, Jia Ning, Chen Renpeng. Soil arch analysis of pile-supported embankments [J]. China Journal of Highway and Transport, 2004, 17(4): 1-6.(in Chinese)
[7] 陈福全, 李阿池, 吕艳平. 桩承式路堤中土拱效应的改进Hewlett算法 [J]. 岩石力学与工程学报, 2007, 26(6): 1278-1283.
  Chen Fuquan, Li Achi, Lü Yanping. An improved solution of Hewletts method for soil arching effect on piled embankments [J]. Chinese Journal of Rock Mechanics and Engineering, 2007, 26(6): 1278-1283.(in Chinese)
[8] 刘吉福. 路堤下复合地基桩、土应力比分析 [J]. 岩石力学与工程学报,2003,22(4):674-677.
  Liu Jifu. Analysis on pile-soil stress ratio for composite ground embankment [J]. Chinese Journal of Rock Mechanics and Engineering, 2003, 22(4): 674-677.(in Chinese)
[9] Chen R P, Chen Y M, Han J, et al. A theoretical solution for pile-supported embankments on soft soil under one-dimensional compression [J]. Canadian Geotechnical Journal, 2008, 45(5): 611-623.
[10] 董必昌, 郑俊杰. CFG 桩复合地基沉降计算方法研究 [J]. 岩石力学与工程学报,2002,21(8):1084-1086.
  Dong Bichang, Zheng Junjie. Study of the settlement calculation of CFG pile composite ground [J]. Chinese Journal of Rock Mechanics and Engineering, 2002, 21(8): 1084-1086.(in Chinese)
[11] Randolph M F, Wroth C P. Analysis of deformation of vertically loaded piles [J]. Journal of Geotechnical Engineering, 1978, 104(12): 1465-1488.
[12] Giroud J P, Bonaparte R, Beech J F, et al. Design of soil layer-geosynthetic systems overlying voids [J]. Geotextiles and Geomembranes, 1990, 9(5): 11-50.
[13] 曹卫平, 陈仁朋, 陈云敏. 桩承式加筋路堤土拱效应试验研究 [J]. 岩土工程学报, 2007, 29(3): 436-441.
  Cao Weiping, Chen Renpeng, Chen Yunmin. Experimental investigation on soil arching in piled reinforced embankments [J]. Chinese Journal of Geotechnical Engineering, 2007, 29(3): 436-441.(in Chinese)
[14] 张浩, 石名磊, 张瑞坤. 桩承式灰土路堤基底荷载效应分析 [J]. 公路交通科技, 2011, 28(6): 25-31.
  Zhang Hao, Shi Minglei, Zhang Ruikun. Analysis on load action effect of subgrade in pile supported lime-soil embankment [J]. Journal of Highway and Transportation Research and Development, 2011, 28(6): 25-31.(in Chinese)

备注/Memo

备注/Memo:
作者简介: 吕伟华(1983—),男,博士生;缪林昌(联系人),男,博士,教授,博士生导师,lc.miao@seu.edu.cn.
基金项目: 国家自然科学基金资助项目(51278099).
引文格式: 吕伟华,缪林昌.刚性桩复合地基桩土应力比计算方法[J].东南大学学报:自然科学版,2013,43(3):624-628. [doi:10.3969/j.issn.1001-0505.2013.03.032]
更新日期/Last Update: 2013-05-20